Sponsored by Deepsite.site

Critical Path Partners forensic scheduling MCP

创建者
danafitkowski6 months ago
13 tools for Primavera P6 forensic delay analysis — AACE windows (29R-03 MIP 3.3), DCMA-14 health checks, Monte Carlo SRA with AACE 122R-22 QRAMM maturity, TIA fragnet (MIP 3.7), collapsed as-built (MIP 3.8), and claim workbench evidence ledger. Open-source CPM engine (MIT) at github.com/danafitkowski/cpp-cpm-engine. Daubert-disclosed methodology. 66-jurisdiction holiday calendars. SHA-256 topology hash on every output. Live hosted at https://mcp.criticalpathpartners.ca/mcp (Streamable HTTP transport).
概览

cpm-engine

npm version license: MIT tests: 528 passing crossval: 153/153 Daubert: disclosed AACE: 29R--03 / 49R--06 / 52R--06

The forensically-defensible CPM engine. AACE-canonical. Daubert-disclosed. Bit-identical between JavaScript and Python.

Maintained by Critical Path Partners — a forensic-scheduling consultancy.


Quick start

npm install @critical-path-partners/cpm-engine
const E = require('@critical-path-partners/cpm-engine');

const result = E.computeCPM(
    [
        { code: 'A', duration_days: 5, early_start: '2026-01-05', clndr_id: 'MF' },
        { code: 'B', duration_days: 3, clndr_id: 'MF' },
        { code: 'C', duration_days: 4, clndr_id: 'MF' },
    ],
    [
        { from_code: 'A', to_code: 'B', type: 'FS', lag_days: 0 },
        { from_code: 'B', to_code: 'C', type: 'FS', lag_days: 0 },
    ],
    {
        dataDate: '2026-01-05',
        calMap: { MF: { work_days: [1, 2, 3, 4, 5], holidays: [] } },
    }
);

console.log('Project finish:', result.projectFinish);     // 2026-01-21
console.log('Critical path:', result.criticalCodesArray); // ['A', 'B', 'C']
console.log('Engine version:', result.manifest.engine_version); // 2.8.0

That's it. Forward pass, backward pass, total float, free float, calendar arithmetic, P6-conventional date math, multi-jurisdiction holidays — all done.


Why this engine?

Capabilitycpm-engineSmartPMAcumen FusePhoenix
Open sourceyesnonono
AACE-canonical method labels (29R-03 / 49R-06 / 52R-06)yespartialpartialpartial
FRE 707 / Daubert disclosure (built-in)yesnonono
JS-Python bit-identical parityyesn/an/an/a
Topology fingerprint hash (SHA-256, copy-detection)yesnonono
Kinematic delay dynamics (velocity / accel / jerk)yesnonono
Bayesian update with hierarchical poolingyesnonono
Multi-jurisdiction holiday calendars (66 jurisdictions)yespartialpartialpartial
MIT licensedyesnonono

The engine math is a commodity. The competitive moat in forensic scheduling is the workflow, the discipline, and the Daubert posture — not the forward pass. Critical Path Partners open-sources the engine so any academic, any solo forensic, any contractor's internal scheduler can build on a defensible foundation.


What you can build

  • Forensic delay analysis — windows analysis (AACE MIP 3.3), collapsed as-built (MIP 3.8), prospective TIA (MIP 3.6)
  • Claim packages — owner-submission EOT bundles with cover letter, exhibits, mitigation logs
  • Daubert disclosures — FRCP 26(a)(2)(B) reports, FRE 702/707 four-prong methodology statements
  • Schedule risk analysis — Monte Carlo P10/P50/P80/P90, sensitivity tornadoes, Bayesian updates
  • Schedule health — DCMA-14 assessment, A-F auto-grade, baseline-vs-current diff
  • Multi-jurisdiction calendars — 66 jurisdictions (CA-FED + 13 provinces, US-FED + 50 states + DC)

AACE alignment

The engine implements the math behind these AACE Recommended Practices:

RPTitleMethod labels emitted
29R-03Forensic Schedule AnalysisMIP 3.3 / 3.5 / 3.6 / 3.8
49R-06Identifying the Critical PathLPM, TFM, MFP
52R-06Prospective Time Impact AnalysisMIP 3.6 prospective
122R-22Quantitative Risk Analysis Maturity Model (QRAMM)(badge surface)
PPG #20 (2nd Ed 2024)Forensic Schedule Analysis Practice Guide(general acceptance)

Method labels are emitted in result.manifest.methodology — exactly the strings AACE peer-reviewers and opposing experts expect.


Verifiable provenance

Every computation emits a manifest:

result.manifest = {
    engine_version: '2.8.0',
    method_id: 'computeCPM',
    activity_count: 3,
    relationship_count: 2,
    data_date: '2026-01-05',
    calendar_count: 1,
    computed_at: '2026-05-10T14:32:01.847Z',
}

Plus, for forensic provenance, every input carries a SHA-256 topology hash:

const hash = E.computeTopologyHash(activities, relationships);
console.log(hash.topology_hash);  // 64-char hex over canonical (code, duration, sorted preds)
// Two XERs with identical hashes ARE the same schedule, regardless of UID rotation.

This is the single most important forensic feature in the engine. Bid-collusion detection, retroactive-manipulation detection, and copy-detection across XERs all rely on it. It is also the foundation that lets opposing counsel verify a CPP analysis post-hoc.


JavaScript - Python parity

The engine has a Python sibling (_cpp_common/scripts/cpm.py) used by every CPP forensic skill. The two implementations are kept bit-identical via cross-validation:

npm run crossval
# 13 fixtures × 153 checks. 0 deviations as of v2.8.0.

Plus a 282-activity real-XER stress test reports 0 mismatches.

This means a forensic analysis run in JavaScript (browser, Node) produces the same numbers as one run in Python (claims-preparation skill, MCP server, batch pipeline). Every CPP deliverable carries the same manifest regardless of which surface produced it.


Production use

The engine runs live at mcp.criticalpathpartners.ca — try it in your browser. The same cpm-engine.js file is served over the wire and embedded inline in every report CPP produces.

The CPP forensic suite (forensic-delay-analysis, claims-preparation, claim-workbench, time-impact-analysis, schedule-risk-analysis, collapsed-as-built, counter-claim-analysis) all consume this engine — the JS port for browser/MCP, the Python sibling for batch pipelines.


Citation

If you use this engine in academic work or expert-witness reports, please cite:

Fitkowski, D. (2026). cpm-engine: A forensically-defensible critical-path-method engine with AACE-canonical method labels and Daubert disclosure. Critical Path Partners. Version 2.8.0. https://github.com/danafitkowski/cpp-cpm-engine

Algorithm citations are in docs/citations.md. All citations have been verified against primary sources.


License

MIT — see LICENSE.

You can use this engine in commercial forensic consulting, in academic research, in your own scheduling product, in court-filed expert reports. Just keep the copyright notice. No support is implied; no warranty is provided. You are responsible for the conclusions you draw with the engine. A Daubert disclosure is built in (DAUBERT.md) — you may use it as a starting point for your own FRCP 26(a)(2)(B) report.


Release notes

v2.9.1 (2026-05-10) — synchronized release marker. Engine code (cpm-engine.js) is byte-identical to v2.8.0; the SHA-256 topology hash algorithm and all CPM math are unchanged. The tag exists because the surrounding CPP skill suite absorbed an emergency truncation-purge hotfix — 80+ data-truncation sites removed across 13 renderers, enforcing the discipline described in feedback_no_truncation.md: analyst-facing data must never be silently cropped. A new regression test (tests/test_no_data_truncation.py) blocks future violations at CI.

v2.8.0 (2026-05-10) — initial public release. See CHANGELOG.md.


Contributing

See CONTRIBUTING.md. Forensic correctness is enforced — every commit must pass 528 unit tests and 153 cross-validation checks. New citations require WebSearch-verified URLs. No fabricated case names. No LLM-generated narratives in core engine paths.


Companion repositories

Two companion repositories are public and consume this engine:

Additional CPP skills (forensic-delay-analysis, claims-preparation, claim-workbench, time-impact-analysis, collapsed-as-built, counter-claim-analysis, schedule-risk-analysis) are private; contact Critical Path Partners for access.


Strategic note

CPP is a forensic-scheduling consultancy. The engine is open-source not as a loss-leader but as a deliberate inversion of the competitive landscape: the math is a commodity, the workflow and discipline are not. Every academic, every solo forensic, every contractor's internal scheduler now has a reason to install CPP and a citation pathway. The closed-engine competitors — SmartPM, ALICE, Nodes&Links, Acumen — cannot match this move because their valuations require the engine stay proprietary.

If you ship something built on this engine, we'd love to hear about it: danafitkowski@gmail.com.

服务器配置

{
  "mcpServers": {
    "criticalpathpartners": {
      "url": "https://mcp.criticalpathpartners.ca/mcp",
      "transport": "streamableHttp"
    }
  }
}
推荐的 MCP Server
TraeBuild with Free GPT-4.1 & Claude 3.7. Fully MCP-Ready.
AiimagemultistyleA Model Context Protocol (MCP) server for image generation and manipulation using fal.ai's Stable Diffusion model.
Baidu Map百度地图核心API现已全面兼容MCP协议,是国内首家兼容MCP协议的地图服务商。
Visual Studio Code - Open Source ("Code - OSS")Visual Studio Code
WindsurfThe new purpose-built IDE to harness magic
Howtocook Mcp基于Anduin2017 / HowToCook (程序员在家做饭指南)的mcp server,帮你推荐菜谱、规划膳食,解决“今天吃什么“的世纪难题; Based on Anduin2017/HowToCook (Programmer's Guide to Cooking at Home), MCP Server helps you recommend recipes, plan meals, and solve the century old problem of "what to eat today"
RedisA Model Context Protocol server that provides access to Redis databases. This server enables LLMs to interact with Redis key-value stores through a set of standardized tools.
BlenderBlenderMCP connects Blender to Claude AI through the Model Context Protocol (MCP), allowing Claude to directly interact with and control Blender. This integration enables prompt assisted 3D modeling, scene creation, and manipulation.
MCP AdvisorMCP Advisor & Installation - Use the right MCP server for your needs
EdgeOne Pages MCPAn MCP service designed for deploying HTML content to EdgeOne Pages and obtaining an accessible public URL.
Zhipu Web SearchZhipu Web Search MCP Server is a search engine specifically designed for large models. It integrates four search engines, allowing users to flexibly compare and switch between them. Building upon the web crawling and ranking capabilities of traditional search engines, it enhances intent recognition capabilities, returning results more suitable for large model processing (such as webpage titles, URLs, summaries, site names, site icons, etc.). This helps AI applications achieve "dynamic knowledge acquisition" and "precise scenario adaptation" capabilities.
ChatWiseThe second fastest AI chatbot™
MiniMax MCPOfficial MiniMax Model Context Protocol (MCP) server that enables interaction with powerful Text to Speech, image generation and video generation APIs.
CursorThe AI Code Editor
Serper MCP ServerA Serper MCP Server
Tavily Mcp
Y GuiA web-based graphical interface for AI chat interactions with support for multiple AI models and MCP (Model Context Protocol) servers.
Jina AI MCP ToolsA Model Context Protocol (MCP) server that integrates with Jina AI Search Foundation APIs.
Amap Maps高德地图官方 MCP Server
Playwright McpPlaywright MCP server
DeepChatYour AI Partner on Desktop